Water Project ITEMS COMPLETED:

​

--✓30,000 gallon storage tank on west side

--✓18 residential water meters

--✓approx 2100' new 8" water line

--✓approx 400' of new 4" water line

--✓new fire hydrants for east side D lots and 

   Back of the Arch Drive, west side

--✓West side and East side storage tanks & well pumps connected under Hwy 191.​​

--✓finish grading roads

--✓rake and reseed disturbed work areas

--✓install East side pump 

--✓install electronic system that monitors storage water levels, well pumps and meters-90% completed

​​

TO DO:

--rake and reseed west side by tanks

--install new well 2 pump (just had pump failure early Dec)

--final runthrough of electronic system

--final inspection of east side pump

Payments go to: Wilson Arch SSD, P.O. Box 97, La Sal, Utah 84530